Accelerated Irrigation Benefit Programme (AIBP) was launched by Union Government in 1996-97 to provide central assistance in the form of loan to State Government to complete those ongoing irrigation projects which were costing Rs.1000 crore or above and were in advanced stage of completion. Subsequently the criteria for inclusion of irrigation projects under AIBP were changed from time to time so as to include all categories of projects i.e. major, medium and minor (surface irrigation) projects to bring regional balance. From 2005-06 onwards, central assistance is now provided in form of grant till 2011-12. A total sum of Rs. 49297.39 crore has been provided to State Governments in form of Central assistance under AIBP till September 2012 out of which Rs 44650.95 crore is for Major & Medium Irrigation Projects and Rs.8278.06 crore is for Minor Irrigation projects. Irrigation potential created from Major & Medium projects under AIBP till March, 2011 is. 63.46 lakh hectare, while that created through Minor projects is 8.88 Lakh ha (upto January, 2011). Since inception altogether 293 major/medium projects have been included under AIBP out of which 141 projects have been completed and 5 projects have been deferred, leaving 147 projects as ongoing. Similarly, total 12768 surface Minor Irrigation Schemes have been sanctioned since inception of AIBP, out of which 9125 schemes have been completed.

Important features of guidelines for release of central assistance to states under AIBP are as under:-

  1. Major/medium projects including Extension Renovation & Modernization projects benefiting drought prone/tribal areas and flood prone areas are eligible for 90% grant assistance.
  2. Major/medium projects in the Special Category States and projects in undivided Karaput, Bolangir and Kalahandi districts of Orissa are also eligible for 90% grant assistance.
  3. Other major/medium projects are eligible for 25% grant assistance under AIBP.
  4. Surface MI schemes fulfilling criteria specified in the guidelines of the Special Category States are eligible for 90% grant assistance and surface MI schemes of the non special category states fulfilling eligibility criteria and benefiting drought prone/tribal areas are also eligible for 90% grant assistance.
  5. Maximum time allowed for completion of major/medium projects under AIBP is 4 years excluding the year of inclusion of the project under AIBP.
  6. The Maximum time allowed for completion of surface MI schemes under AIBP is 2 years excluding the year of inclusion of the scheme under AIBP.
  7. The state governments are required to enter into an MOU with the Ministry of Water Resources for timely completion of the project specifying year wise targets of potential creation under AIBP.
  8. A new major/medium project may be included in AIBP only on completion of an ongoing project under AIBP on one to one basis. However, projects benefiting drought prone/tribal areas, projects in the states having irrigation development below national average and projects included in the Prime Minister’s package for agrarian distressed districts of the Andhra Pradesh, Karnataka, Kerala and Maharashtra may be included in AIBP in relaxation to one to one criterion.

The State-Wise status of AIBP project is given as under:

AIBP 2013.jpg

Table: Details of AIBP Projects
Sl.No.Name of Major Medium Irrigation ProjectsAIBP Project Name State Year of inclusion under AIBPStatus (Completed/Ongoing)Year of completion (Rs. Crore)Target Potential under AIBP (Th ha)Latest Estimated Cost of AIBP Components (Rs. Crore)Total CLA/Grant relesaed upto (3/12) (Rs. Crore)Total expenditure incurred upto (3/2011) (Rs. Crore)Total potential created upto(3/2012) (Th ha)
1Ali Sagar Lift Irrigation ProjectAlisagar LISAndhra Pradesh2006-07Completed2006-0721.77227.6916.3788.2721.769
2Gundalakamma Major Irrigation ProjectGundlakdammaAndhra Pradesh2005-06Ongoing32.4781.8599.352428.623.44
3Guthpa (Argul Rajaram) Lift Irrigation ProjectGuthpa LISAndhra Pradesh2006-07Completed2008-0915.69872.9117.572.9115.698
4Indira Sagar /Polavaram Major Irrigation ProjectIndira Sagar (Polavaram)Andhra Pradesh2008-09Ongoing4365,974.72562.4691,987.780
5Jurala (Priyadarshini) Major Irrigation ProjectPriyadarshini JuralaAndhra Pradesh1997-98Completed2006-0740.16459.9245.189451.60840.16
6Nagarjuna Sagar Major Irrigation ProjectNagarjunsagarAndhra Pradesh1998-99Completed2005-0627.94487.3277.1477.9227.944
7Pushkaram Lift Irrigation ProjectPushkara LISAndhra Pradesh2006-07Ongoing71.184196.2447.085378.5448.559
8Somasila Major Irrigation ProjectSomasilaAndhra Pradesh1997-98Completed2006-0738.475230.081164.525263.90939.774
9Sriram Sagar Stage - I (Pochampad) Major Irrigation ProjectSriramsagar St.IAndhra Pradesh1996-97Completed2005-06137.04568.42327.17512.31137.04
10Tadipudi Lift Irrigation ProjectTadipudi LISAndhra Pradesh2006-07Ongoing83.609285.7448.22335.2350.601
11Thotapalli Barrage Major Irrigation ProjectThotapally Barrage Andhra Pradesh2005-06Ongoing48.563420.9499.731405.8225.9
12Vamsadhara Stage - II Phase - I Major Irrigation ProjectVamsdhara St-II Ph IAndhra Pradesh2003-04Completed2008-0917.10386.81137.11682.78624.487
13Annamayya (Cheyyeru) Medium Irrigation ProjectCheyyeru(Annamaya)Andhra Pradesh1996-97Completed2003-049.10547.1425.3347.149.105
14Gollavagu Medium Irrigation ProjectGollavaguAndhra Pradesh2006-07Ongoing3.84575.6860.4762.540.607
15Gundlavagu Medium Irrigation ProjectGundalavaguAndhra Pradesh2000-01Completed2006-071.04514.754.00511.041.045
16Kanupur Canal Medium Irrigation ProjectKanupur CanalAndhra Pradesh2000-01Deffered0.5619.781.921.420
17Maddigedda Medium Irrigation ProjectMaddigeddaAndhra Pradesh2000-01Completed2006-071.4157.23.7926.711.415
18Madduvalasa Medium Irrigation ProjectMadduvalasaAndhra Pradesh1998-99Completed2005-0610103.54866.894.44810
19Mathadivagu Medium Irrigation ProjectMathadivaguAndhra Pradesh2006-07Ongoing3.4442.2137.0244.342.024
20Musurumilli Medium Irrigation ProjectMusurumilliAndhra Pradesh2007-08Ongoing9.164153.5285.742127.086.537
21Palemvagu Medium Irrigation ProjectPalemvagu Andhra Pradesh2005-06Ongoing4.163.579.53669.0440
22Neelwai Medium Irrigation ProjectNeelwai Andhra Pradesh2006-07Ongoing5.2677.7718.466.550
23Ralivagu Medium Irrigation ProjectRalivaguAndhra Pradesh2006-07Ongoing2.42829.826.7137.721.012
24Sri Komarambheem Medium Irrigation ProjectSri Komaram BheemAndhra Pradesh2006-07Ongoing9.915201.74145.54281.420
25Swarnamukhi Barrage Medium Irrigation ProjectSwarnamukhiAndhra Pradesh2005-06Completed2008-094.65679.0811.86239.873.651
26Tarakarama Thirtha Sagaram Medium Irrigation ProjectTarakarama thirtha Sagaram Andhra Pradesh2005-06Ongoing10220.0433.00667.4530
27Veligallu Medium Irrigation ProjectVeligalluAndhra Pradesh2006-07Completed2008-099.71372.5162.33663.8539.713
28Yerrakalva Medium Irrigation ProjectYerrakalva Res.Andhra Pradesh2000-01Ongoing6.96189.5728.46372.0675.06
29Jclis - Glis St-I, II, III Major Irrigation Project_Andhra PradeshJ. Chokka Rao LISAndhra Pradesh2006-07Ongoing2498,200.711,139.2614,238.4616.188
30Peddavagu Medium Irrigation ProjectPeddavaguAndhra Pradesh2006-07Ongoing6.073124.64106.02556.540
31FFC from SRSP (Indiramma Flood Flow canal)FFC of SRSPAndhra Pradesh2005-06Ongoing403,002.47382.42,134.420
32Rajiv Bhima Lift Irrigation ProjectRajiv Bhima LISAndhra Pradesh2007-08Ongoing82.1531,3771,165.671853.180
33SRSP - II Major Irrigation ProjectSRSP St.IIAndhra Pradesh2005-06Ongoing178.066736.58139.467505.81119.416
34Modernization of JamunaMod. of Jamuna Irr.Assam2001-02Completed2008-0913.75859.76936.36353.14312.7
35Buridihing Lift Irrigation ProjectBurhi Dihing liftAssam1997-98Ongoing4.4915.1994.2249.5552.425
36Hawaipur Lift Irrigation ProjectHawaipur liftAssam1996-97Completed2006-073.8879.664.9658.723.887
37Rupahi Medium Irrigation ProjectRupahi Lift Assam1996-97Completed2001-022.7681.6550.6552.1772.768
38Dhansiri Major Irrigation ProjectDhansiriAssam1996-97Ongoing68.366267.892145.597180.98341.258
39Bordikarai Major Irrigation ProjectBordikaraiAssam1997-98Completed2004-057.40619.5067.01319.4597.203
40Champamati Major Irrigation ProjectChampamatiAssam1996-97Ongoing24.994273.9466.23751.8489.746
41Integrated Kallong Basin Lift Irrigation ProjectIntg. Irr. Scheme in Kollong Basin Assam1997-98Completed2006-078.64771.0812.98233.63.775
42Borolia Medium Irrigation ProjectBoroliaAssam1996-97Ongoing13.562107.1429.80252.9683.3
43Pahumara Medium Irrigation ProjectPahumaraAssam1996-97Completed2008-0911.75519.4169.2918.06710.551
44Sone Barrage Remodelling And Link CanalSone ModernisationBihar1998-99Completed2008-09314.58664.258168.449635.491290.58
45Bansagar Dam Major Irrigation Project_BiharBansagarBihar1997-98Ongoing94366.82583.5334.8660
46Batane Major Irrigation Project_Bihar BataneBihar2000-01Ongoing4.80677.0243.33540.660
47Bilasi Medium Irrigation ProjectBilasi Reservoir Bihar1997-98Completed2000-01416.7623.3916.7624
48Durgavati Major Irrigation ProjectDurgawatiBihar1996-97Ongoing20.297896.6565.09399.5113.3
49Orni Medium Irrigation ProjectOrni ReservoirBihar1997-98Completed2006-079.55728.88311.40129.1179.459
50Punpun Barrage Major Irrigation ProjectPunpunBihar2007-08Ongoing13.68619.08643.884196.1850
51Upper Kiul Major Irrigation ProjectUpper KiulBihar1996-97Completed2006-0711.6894.50722.57983.48510.18
52Western Kosi Canal Major Irrigation ProjectWestern KosiBihar1996-97Ongoing212.051,069.25252.099986.038145.675
53KharungKharung(ERM)Chhattisgarh2010-11Ongoing10.345.94.510.895
54Maniyari Maniyari Tank (ERM)Chhattisgarh2011-12Ongoing11.478159.9522.2520
55Barnai Medium Irrigation ProjectBarnai Chhattisgarh2002-03Completed2006-071.5082.652.654.9141.508
56Jonk Diversion Major Irrigation ProjectJonk DiversionChhattisgarh1999-2000Completed2006-079.56917.627.616.0487.87
57Kosarteda Medium Irrigation ProjectKosertedaChhattisgarh2002-03Ongoing11.12138.2854.773130.1826.5
58Kelo Major Irrigation ProjectKelo ProjectChhattisgarh2008-09Ongoing22.81482.227.023243.490
59Mahanadi Major Irrigation ProjectMahanadi Res ProjectChhattisgarh2005-06Completed2010-1113.883235.6726.954284.6813.76
60Shivnath Medium Irrigation ProjectShivnath DiversionChhattisgarh1997-98Completed2002-035.2386.643.546.5615.238
61Sutiapat Medium Irrigation ProjectSutiapat Chhattisgarh2010-11Ongoing2.937.3556.3187.0980.6
62Hasdeo Bango Major Irrigation ProjectHasdeo BangoChhattisgarh1997-98Completed2006-0786.5304.74243.78390.75686.5
63Hasdeo Bango Major Irrigation ProjectMinimata (Hasdeo Bango Ph. IV)Chhattisgarh2007-08Completed2010-1138.4111.0866.00497.0838.4
64Salaulim Major Irrigation ProjectSalauli Ph-IGoa1997-98Completed2006-079.329.6917.7526.5179.3
65Tillari Major Irrigation Project_GoaTillariGoa2000-01Ongoing14.521409.922247.42238.7688.747
66Sipu Major Irrigation ProjectSipu Gujarat1996-97Completed1999-20001.01616.9056.45515.9851.016
67Watrak Major Irrigation ProjectWatrak Gujarat1997-98Completed1999-20003.7149.363.119.2113.714
68Damanganga Major Irrigation Project_Gujarat Damanganga Gujarat1997-98Completed1999-20006.68628.4849.4728.4846.686
69Karjan Major Irrigation ProjectKarjan Gujarat1997-98Completed1999-20005.98917.27.617.685.989
70Sukhi Major Irrigation ProjectSukhi Gujarat1997-98Completed1999-20003.48813.685.6513.333.488
71Umaria Medium Irrigation ProjectUmaria Gujarat1996-97Completed1996-970.1620.60.1350.60.162
72Harnav - II Medium Irrigation ProjectHarnav - II Gujarat1996-97Completed1997-9800.30.0650.30
73Jhuj Medium Irrigation ProjectJhuj Gujarat1996-97Completed1999-20002.90715.794.7415.792.907
74Deo Medium Irrigation ProjectDeo Gujarat1997-98Completed1997-980.1030.470.50.470.103
75Sardar Sarovar Major Irrigation Project_GujaratSardar SarovarGujarat1996-97Ongoing1,79227,150.135,736.77810,736.45545.276
76Mukteshwar Medium Irrigation ProjectMukteshwarGujarat1996-97Completed2006-075.06622.66510.86247.025.066
77Ozat - II Medium Irrigation ProjectOzat-IIGujarat2000-01Completed2009-101.837.93313.688.4333.338
78Aji - IV Medium Irrigation ProjectAji-IVGujarat2000-01Completed2009-103.7556.30614.706126.2323.75
79Bhadar - II Medium Irrigation ProjectBhadar-IIGujarat2002-03Completed2010-111.546.3128.56829.5426
80Brahmini - II Medium Irrigation ProjectBrahmini-IIGujarat2000-01Completed2008-092.06212.45418.3072.062
81Gurgaon Canal Major Irrigation Project_HaryanaGurgaon canalHaryana1996-97Completed2003-043.3412.53.3410
82Jawahar Lal Nehru Lift Irrigation ProjectJ. L. N. Lift Irr.Haryana1997-98Deffered6915.7651215.7650
83Sidhatha Medium Irrigation ProjectSidhataHimachal Pradesh2000-01Ongoing5.3564.49962.5869.8130.823
84Shahnehar Major Irrigation Project_Himachal PradeshShahnehar Irr. projectHimachal Pradesh1997-98Ongoing24.76303.567203.855283.2418.026
85Balh Valley Left Bank Medium Irrigation ProjectBalh Vally (Left Bank)Himachal Pradesh2009-10Ongoing4.35495.39355.22162.9820.94
86Changer Lift Irrigation ProjectChanger LiftHimachal Pradesh2000-01Ongoing3.04187.49557.23877.8343.041
87Modernisation of Kathua Canal Med Irrigation ProjectMod. of Kathua CanalJammu & Kashmir1999-2000Completed2006-073.20711.187.61613.6713.207
88Modernisation of Martand Canal(Medium,Erm)Mod. of Martand CanalJammu & Kashmir2006-07Completed2010-111.78915.03514.89913.5571.789
89Mod Of Ranbir Canal Project (Revised Major) (Erm)Mod. of Ranbir CanalJammu & Kashmir1999-2000Ongoing13.666146.842108.2112.2277.442
90Mod Of New Pratap CanalMod. of New Pratap CanalJammu & Kashmir1999-2000Ongoing2.61944.6733.10431.1982.348
91Mod of Zaingir CanalMod. of Zaingir CanalJammu & Kashmir2001-02Completed2006-072.146.6424.8496.0232.14
92Mod. of Ahaji Canal Medium Irrigation ProjectMod. of Ahji CanalJammu & Kashmir2008-09Ongoing2.21515.63312.0918.0720.73
93Mod. of Babul Canal(Medium,Erm) ProjectMod. of Babul Canal Jammu & Kashmir2007-08Completed2011-120.6898.6046.7584.70.289
94Mod. of Dadi Canal Medium Irrigation SchemeMod. of Dadi CanalJammu & Kashmir2006-07Ongoing2.57338.8534.50235.0811.973
95Mod. of Mavkhul Canal Medium Irrigation ProjectMod. of Mav KhulJammu & Kashmir2006-07Completed2010-112.5478.1847.1053.232.547
96Modernisation of ravi canalRestoration & Mod. Of Main Ravi CanalJammu & Kashmir2011-12Ongoing38.51755.68.9100
97Igo Phey (Ego-Phey Canal) Medium Irrigation ProjectIgopheyJammu & Kashmir2000-01Completed2006-073.47314.049.6313.673.473
98Kandi Canal Medium Irrigation ProjectMod. Kandi Canal Jammu & Kashmir2007-08Ongoing3.22952.9116.200
99Koil Lift Irrigation ProjectKoil LiftJammu & Kashmir1996-97Completed2006-072.15-0.500
100Lethpora Lift Irrigation ProjectLethpora LiftJammu & Kashmir1996-97Completed2006-072.6583.133.3163.0272.656
101Marval Lift Irrigation ProjectMarwal LiftJammu & Kashmir1996-97Completed2006-0711.39-0.300
102Rafiabad High Lift Irrigation ProjectRafiabad High Lift Irr.Jammu & Kashmir2001-02Completed2010-112.93243.71835.32344.5292.932
103Rajpora Lift Irrigation ProjectRajpora LiftJammu & Kashmir2000-01Ongoing2.4364.57953.08255.2711.593
104Tral Lift /Gral Lift Irrigation ProjectTral LiftJammu & Kashmir2000-01Ongoing6132.0763.5256.4380.91
105Parkachick Khawas Medium Irrigation ProjectPrakachik Khows CanalJammu & Kashmir2007-08Ongoing2.26234.948.4426.5540.4
106Gumani Barrage Major Irrigation ProjectGumaniJharkhand1997-98Ongoing16.194161.71731.402128.3620
107Kansjore Medium Irrigation ProjectKansjore Jharkhand1997-98Ongoing6.26434.411.0436.2556.264
108Latratu Medium Irrigation ProjectLatratu Jharkhand1997-98Completed2002-036.14.672.134.676.1
109Panch Khero Medium Irrigation ProjectPanchkheroJharkhand2004-05Ongoing3.08554.6498.24247.2260
110Sonua Medium Irrigation ProjectSonuaJharkhand1997-98Ongoing8.00861.13919.24654.2120
111Subernarekha Multipurpose Project_JharkhandSubernarekha Multipurpose Jharkhand2011-12Ongoing874.6335.544.555
112Surangi Medium Irrigation ProjectSurangiJharkhand1997-98Ongoing2.60134.70613.28431.0070
113Tapkara Medium Irrigation ProjectTapkara Reservoir Jharkhand1997-98Completed2002-031.8190.860.5150.861.52
114Upper Sankh Medium Irrigation ProjectUpper SankhJharkhand2004-05Ongoing7.06989.06426.3580.9570.4
115Modernisation of Bhadra canalMod. Canal System of Bhadra Reservoir Canal System (ERM)Karnataka2008-09Ongoing24.1149321721.6147.561
116Renovation & Restoration of Bheemasamudra Tank & its canalRestoration Bhimasamundra TankKarnataka2009-10Ongoing0.88.65556.1240.0080
117Upper Krishna Stage - I Major Irrigation ProjectUpper Krishna St.I Karnataka1996-97Ongoing243.9042,135.41,380.6632,120.679148.799
118Bhima Lift Irrigation ProjectBhima LISKarnataka2009-10Ongoing24.292551.93156.6227.150.581
119Gandorinala Medium Irrigation ProjectGandori NalaKarnataka2001-02Ongoing8.094214.17113.911172.627.943
120Guddada Mallapura Medium Irrigation ProjectGuddada Malapura LiftKarnataka2009-10Ongoing5.261115.457.24352.8260
121Ghataprabha Major Irrigation ProjectGhataprabha St.IIIKarnataka1997-98Completed2010-11148.8778.9447.283823.256111.574
122Hippargi Major Irrigation ProjectHipparagi LISKarnataka2008-09Ongoing74.7421,254.98640.37553.39931.813
123Hirehalla Medium Irrigation ProjectHirehallaKarnataka1996-97Completed2006-078.33157.9264.24128.454.18
124Karanja Major Irrigation ProjectKaranjaKarnataka1997-98Ongoing30.966481.427189.03251.7718.119
125Malaprabha Major Irrigation ProjectMalaprabhaKarnataka1996-97Ongoing48.09387.42359.545358.00649.031
126Maskinala Medium Irrigation ProjectMaskinallahKarnataka2002-03Completed2003-043.0013.8353.223.8353.502
127Upper Krishna Stage - II Major Irrigation ProjectUpper Krishna St.IIKarnataka2001-02Ongoing178.3213,151.7341,517.3092,700.37165.247
128Varahi Major Irrigation ProjectVarahiKarnataka2007-08Ongoing15.56405.2968.535247.940.383
129Votehole Medium Irrigation ProjectVoteholeKarnataka2007-08Completed2008-0901.30.2900
130Dolaithabi Barrage Medium Irrigation ProjectDudhgangaKarnataka2008-09Ongoing11.367727.50626.630
131Chitturpuzha Major Irrigation ProjectChitturpuzha Kerala2010-11Ongoing4.96434.575.8524.9796.226
132Kanhirapuzha Major Irrigation ProjectKanhirapuzhaKerala2008-09Ongoing1.247305.0714.3181.24
133Kallada Major Irrigation ProjectKalladaKerala1996-97Completed2004-059.27667.96532.564.669.276
134Muvattupuzha Major Irrigation ProjectMuvattupuzhaKerala2000-01Ongoing32.105293133.129286.34625.654
135Karapuzha Medium Irrigation ProjectKarapuzhaKerala2006-07Ongoing9.8741282.7199.4250.608
136Banjar River Project Medium Irrigation Project_Madhya PradeshBanjar Madhya Pradesh2000-01Completed2002-031.0952.381.1962.381.095
137Bansagar Unit - II Major Irrigation ProjectBansagar Unit-II(CCA)Madhya Pradesh2003-04Ongoing154.5431,851.78368.4281,932.484128.744
138Bargi Diversion Major Irrigation ProjectBargi Diversion Ph - IMadhya Pradesh2001-02Ongoing21.194411140.645392.05615.248
139Bargi Diversion Major Irrigation ProjectBargi Diversion Ph -I IMadhya Pradesh2002-03Ongoing31.899322.71125.54281.12221.584
140Bargi Diversion Major Irrigation ProjectBargi Diversion Ph -I I IMadhya Pradesh2007-08Ongoing261,229.1555.994325.820
141Bargi Diversion Major Irrigation ProjectBargi Diversion Ph-IVMadhya Pradesh2008-09Ongoing34751.037.369176.040
142Bariyarpur Left Bank Canal Major Irrigation ProjectBariarpur LBCMadhya Pradesh2000-01Ongoing43.85365.78100.581258.7332.46
143Bawanthadi Major Irrigation Project_Madhya PradeshBawanthadiMadhya Pradesh2003-04Ongoing29.412587.1691.959221.98128.018
144Indira Sagar /Narmada Sagar Project Major Irrigation ProjectIndira Sagar Canal Ph. IIIMadhya Pradesh2007-08Ongoing20.7704.4686.26232.760
145Indira Sagar /Narmada Sagar Project Major Irrigation ProjectIndira Sagar Unit IVMadhya Pradesh2008-09Ongoing19.6298.0148.48353.430
146Indira Sagar /Narmada Sagar Project Major Irrigation ProjectIndira Sagar Unit- II (CCA)Madhya Pradesh1996-97Ongoing62.21,354.67696.8231,226.79535.78
147Jobat (Shahid Chandra Shekhar Azad Sagar) Major Irrigation ProjectJobatMadhya Pradesh2010-11Ongoing2.84841.016.667.312.048
148Lower Goi Major Irrigation ProjectLower GoiMadhya Pradesh2008-09Ongoing15.686332.71170.683130.7150
149Mahan (Gulab Sagar) Major Irrigation ProjectMahanMadhya Pradesh2003-04Ongoing19.74395.1131.48187.889
150Mahi Major Irrigation ProjectMahiMadhya Pradesh2000-01Ongoing26.43490.28309.625347.6226.43
151Omkareshwar Major Irrigation ProjectOmkareshwar Phase I (CCA)Madhya Pradesh2003-04Ongoing24576.64164.283426.16910.8
152Omkareshwar Major Irrigation ProjectOmkareshwar, Ph.-IIMadhya Pradesh2007-08Ongoing19.578287.06111.853142.990.3
153Omkareshwar Major Irrigation ProjectOmkareshwar, Ph.-IIIMadhya Pradesh2007-08Ongoing48.592482.3682.086239.0217.2
154Pench Diversion Major Irrigation ProjectPench Div-IMadhya Pradesh2007-08Ongoing28.26834216.378232.720
155Punasa Lift Irrigation ProjectPunasa LISMadhya Pradesh2008-09Ongoing35.008464.17381.267391.2212.6
156Rajghat Unit - I Dam Major Irrigation Project_Madhya Pradesh Rajghat Dam (Completed)Madhya Pradesh1998-99Completed2004-05063363.210
157Sagad Medium Irrigation ProjectSagar(Sagad)Madhya Pradesh2011-12Ongoing17.061129.0614.75100
158Sanjay Sagar (Gomukh ) Medium Irrigation ProjectSanjay Sagar (Bah)Madhya Pradesh2011-12Ongoing17.807161.5312.97500
159Upper Wainganga (Sanjay Sarovar) Major Irrigation ProjectUpper Wainganga Madhya Pradesh1996-97Completed2002-0328.255100.7450.106100.7428.255
160Sindh Phase - II Major Irrigation ProjectSindh Phase IIMadhya Pradesh1998-99Ongoing159.0471,862.42474.4861,157.2381.91
161Sindh Phase - I Major Irrigation ProjectSindh Phase IMadhya Pradesh1999-2000Completed2007-0810.5821.8414.87628.2385.212
162Singhpur Medium Irrigation ProjectSinghpurMadhya Pradesh2011-12Ongoing10.2128.815.7500
163Upper Beda Medium Irrigation ProjectUpper BedaMadhya Pradesh2008-09Ongoing9.917208.688.348103.227.393
164Urmil RBC Medium Irrigation Project_Madhya PradeshUrmil R.B.C. Madhya Pradesh2000-01Completed2002-032.1234.812.3914.812.123
165Bansagar Dam Major Irrigation Project_Madhya Pradesh Bansagar Unit-IMadhya Pradesh1996-97Completed2010-1101,379.07364.984980.820
166Indirasagar Dam (Unit - I)Indira Sagar Unit- I Madhya Pradesh1996-97Ongoing5,1502464,755.620
167Sangola Branch Canal Irrigation ProjectSangola Branch CanalMaharashtra2007-08Ongoing11.288183.24139.0695.565.815
168Tarali Major Irrigation ProjectTaraliMaharashtra2007-08Ongoing14.276481.66184.34217.553.766
169Chandrabhaga Medium Irrigation ProjectChandarbhagaMaharashtra2007-08Completed2009-101.9226.9122.6921.061.924
170Pothara Nalla Medium Irrigation ProjectPothra NallaMaharashtra2006-07Completed2008-095.15918.6820.59217.15.159
171Khadakwasla Major Irrigation ProjectKhadakwaslaMaharashtra2002-03Completed2004-050.6245.565.565.560.624
172Krishna Major Irrigation ProjectKrishnaMaharashtra2002-03Completed2008-0919.588262213.107217.18519.588
173Bhima Major Irrigation ProjectBhimaMaharashtra1997-98Completed2006-0758.7581,058.9944.505168.5544.017
174Kukadi Major Irrigation ProjectKukadi(CCA)Maharashtra2002-03Completed2008-0953.143463.4270.186337.5840.715
175Warna Major Irrigation ProjectWarnaMaharashtra2005-06Ongoing54.74958569.395229.145.875
176Upper Tapi Major Irrigation ProjectUpper TapiMaharashtra1997-98Completed2004-051.39817.67.717.51.398
177Upper Penganga Major Irrigation ProjectUpper PengangaMaharashtra2004-05Ongoing44.4721,511.82230.266397.5625.113
178Upper Wardha Major Irrigation ProjectUpper WardhaMaharashtra1997-98Completed2008-0937.258988.58247.024380.51734.522
179Waghur Major Irrigation ProjectWaghurMaharashtra1996-97Ongoing38.571,058.99363.752354.56313.655
180Chaskaman Major Irrigation ProjectChaskamanMaharashtra2002-03Completed2008-0926.18911495.378129.02824.996
181Nandur Madhameshwar Major Irrigation ProjectNandur MadhmeshwarMaharashtra2006-07Completed2008-0924.623269.03218.702196.8232.246
182Nandur Madhameshwar Major Irrigation ProjectNandur Madhmeshwar Ph-IIMaharashtra2009-10Ongoing20.5195.41128.7138.460
183Jayakwadi Stage - II Major Irrigation ProjectJayakwadi Stage-IIMaharashtra2000-01Completed2004-057.27391.4843.73591.487.273
184Surya Major Irrigation ProjectSuryaMaharashtra1996-97Completed2006-072.96872.8413.5554.7680.46
185Bawanthadi Major Irrigation Project_MaharashtraBawanthadiMaharashtra2004-05Ongoing27.708678.81145.67464.4822.203
186Lower Godavari (Vishnupuri) Major Irrigation ProjectVishnupuriMaharashtra2000-01Completed2005-062.63617.795.4147.382.636
187Gosi Khurd (Indira Sagar) Major Irrigation ProjectGosikhurdMaharashtra1996-97Ongoing231.0817,111.5182,556.1163,349.42525.185
188Lower Wardha Major Irrigation ProjectLower Wardha (W)Maharashtra2006-07Ongoing63.3331,742.85154.688519.6317.379
189Wan River Major Irrigation ProjectWanMaharashtra1998-99Completed2005-0615.275108.6159.564113.3214.921
190Wan River Major Irrigation ProjectWan - IIMaharashtra2006-07Completed2008-095.0811.772.0300
191Arunawati Major Irrigation ProjectArunawati (W)Maharashtra2006-07Completed2008-090.76919.0621.6415.1860.769
192Punad Major Irrigation ProjectPunadMaharashtra2006-07Ongoing10.846161.42137.669109.1438.902
193Bembla Major Irrigation ProjectBemblaMaharashtra2007-08Ongoing52.5431,352.53619.865675.4627.505
194Khadakpurna River Major Irrigation ProjectKhadakpurna (W)Maharashtra2006-07Ongoing24.864693.37534.787477.5313.9
195Krishna Koyna Lift Irrigation ProjectKrishna Koyana LiftMaharashtra2009-10Ongoing104.167973.62347.76241.8320.267
196Lower Dudhana Major Irrigation ProjectLower Dudhna (W)Maharashtra2005-06Ongoing44.4821,056.42177.092580.6810.819
197Dhom Balkawadi Tunnel Major Irrigation ProjectDhom BalakwadiMaharashtra2007-08Ongoing18.1451.9393.786160.135.68
198Bahula Medium Irrigation ProjectBahulaMaharashtra2000-01Completed2006-074.30227.1211.52420.241.668
199Hatiz (Hingni) Medium Irrigation ProjectJawalgaonMaharashtra2002-03Completed2004-051.8072.732.732.731.807
200Kasari Medium Irrigation ProjectKasariMaharashtra2002-03Completed2004-051.2351.513.1951.511.235
201Kumbhi Medium Irrigation ProjectKumbhiMaharashtra2002-03Completed2006-075.43423.2318.619.293.604
202Kadavi Medium Irrigation ProjectKadviMaharashtra2002-03Completed2004-050.3651414140.365
203Dongargaon (Chnadrapur) Medium Irrigation ProjectDongargaonMaharashtra2005-06Ongoing2.76631.2916.89924.0321.977
204Hetwane Major Irrigation ProjectHetwaneMaharashtra2002-03Completed2008-096.168109.4150.49658.4370.546
205Shivana Takli Medium Irrigation ProjectShivna TakliMaharashtra2005-06Completed2008-096.38972.8516.415.046.39
206Patgaon Medium Irrigation ProjectPatgoanMaharashtra2004-05Completed2006-071.99221.513.97521.51.992
207Amrawati Medium Irrigation ProjectAmravati Maharashtra2005-06Completed2007-082.6069.821.1827.822
208Upper Manar Medium Irrigation ProjectUpper Manar(W)Maharashtra2002-03Ongoing8.28338.24279.736209.0114.339
209Kasarsai Medium Irrigation ProjectKasarsaiMaharashtra2002-032004-053.0363.371.6853.373.036
210Tajnapur Phase - I Lift Irrigation ProjectTajnapur LISMaharashtra2006-07Completed2008-093.6228.4726.438.4884.471
211Madan Medium Irrigation ProjectMadan Tank Maharashtra2005-06Completed2008-093.2812.761.5118.541.2
212Gadnadi Medium Irrigation ProjectGadnadiMaharashtra2009-10Ongoing3.473395.1737.8106.20.5
213Lower panzara (Akalpadda) Irrigation ProjectLower PanzaraMaharashtra2009-10Ongoing6.785132.44114.8761.92.075
214Kar Medium Irrigation ProjectKar (W)Maharashtra2006-07Completed2008-093.24478.818.59773.8281.675
215Pentakali Medium Irrigation ProjectPentakliMaharashtra2007-08Completed2009-103.2224.1823.2214.972.1
216Gul Medium Irrigation ProjectGul Maharashtra2005-06Ongoing3.02556.0724.88848.7691.331
217Lal Nalla Medium Irrigation ProjectLal Nalla (W)Maharashtra2006-07Completed2008-097.14439.0820.1727.4393.421
218Prakashe Bhandara Medium Irrigation ProjectPrakasha BarrageMaharashtra2007-08Completed2008-0910.307181.9844.25961.33910.307
219Purna River Medium Irrigation ProjectPurna (W)Maharashtra2006-07Completed2008-097.50759.647.51151.787.507
220Sulwade Barrage Medium Irrigation ProjectSulwade BarrageMaharashtra2007-08Completed2008-098.582133.08269.48474.88.582
221Utawali Medium Irrigation ProjectUtawaliMaharashtra2006-07Completed2008-095.07494.5241.05539.75.074
222Morana Gureghar Medium Irrigation ProjectMorna (Gureghar)Maharashtra2007-08Ongoing3.07568.99.8235.720.085
223Uttarmand Medium Irrigation ProjectUttermandMaharashtra2007-08Ongoing4.7332.977.97422.893.145
224Wang Medium Irrigation ProjectWang ProjectMaharashtra2008-09Ongoing7.06874.6614.52658.1040.615
225Sarangkheda Barrage Medium Irrigation ProjectSarangkhedaMaharashtra2007-08Completed2008-0911.51960.55348.94952.18311.519
226Sapan Medium Irrigation ProjectSapanMaharashtra2007-08Completed2009-104.42690.7978.60579.292.781
227Upper Kundlika Medium Irrigation ProjectUpper KundalikaMaharashtra2008-09Ongoing2.8118.188.72741.7940.84
228Arjuna Medium Irrigation ProjectArjunaMaharashtra2007-08Ongoing9.411333.87266.673216.6920.868
229Kudali Medium Irrigation ProjectKudaliMaharashtra2009-10Ongoing5.3277712.22360
230Lower Pedhi Major Irrigation ProjectLower PedhiMaharashtra2008-09Ongoing17.023255.97219.417154.680
231Nardave Medium Irrigation ProjectNaradave (Mahammadwadi)Maharashtra2009-10Ongoing7.924211.4630.26276.50.462
232Aruna Medium Irrigation ProjectArunaMaharashtra2009-10Ongoing9.027210.4533.862900
233Tillari Major Irrigation Project_MaharashtraTillari (Maharashtra Portion)(W)Maharashtra2005-06Ongoing6.57818.7389.339673.634.354
234Thoubal Major Irrigation ProjectThoubalManipur1997-98Ongoing29.449854.37482.839691.9110.861
235Khuga Major Irrigation ProjectKhugaManipur1996-97Ongoing15301.2163.384313.9610
236Dolaithabi Barrage Medium Irrigation ProjectDolaithabi BarrageManipur2002-03Ongoing7.545195.801121.192159.8630
237Imp. to Sason Canal Improvement to Sason Canal SystemOdisha2002-03Completed2004-0516.28234.9226.00940.1816.282
238Imp. to Salki ProjectImprovement to Salki IrrigationOdisha2003-04Completed2004-0520.148.658.6511.1120.14
239Salandi Major Irrigation ProjectSalandi Left Main Canal- 6.84 km - 14.33 km (Ambahata Canal)Odisha2002-03Completed2005-063.656.56.196.343.65
240Anandpur Barrage Canal Irrigation ProjectAnandpur Barr. Ph.-I / Integrated Anandpur Barr. Odisha1996-97Ongoing5.877617.4783.104272.075.877
241Potteru Major Irrigation ProjectPotteru(KBK) Odisha2001-02Completed2004-057.2831.1225.4364.927.28
242Rengali Project Phase - I Irrigation ProjectRengali Odisha1996-97Ongoing143.49633.49261.564606.74422.515
243Upper Kolab Major Irrigation ProjectUpper Kolab(KBK) Odisha1997-98Completed2004-0521.4103.556.512541.6421.4
244Upper Indravati Multi Purpose ProjectUpper Indravati(KBK) Odisha1996-97Ongoing86.389574.53518.122532.06566.338
245Kanupur Major Irrigation ProjectKanupur Odisha2003-04Ongoing29.578981.533612.751605.7440
246Lower Indra Major Irrigation ProjectLower Indra(KBK) Odisha1999-2000Ongoing38.871,192.456948.339909.58917.16
247Lower Suktel Major Irrigation ProjectLower Suktel(KBK) Odisha1999-2000Ongoing40.424901.24232.388303.030
248Rukura Medium Irrigation ProjectRukura-TribalOdisha2009-10Ongoing7.648112.6454.73727.5510
249Chheligada Medium Irrigation ProjectChheligada DamOdisha2003-04Ongoing3194.09913.12878.8140
250Ret Medium Irrigation ProjectRET Irrigation(KBK) Odisha2003-04Ongoing8.5273.8194.318108.5540
251Subernarekha Major Irrigation ProjectSubernarekha Odisha1996-97Ongoing183.1363,786.781,310.051039.858
252Telengiri Major Irrigation ProjectTelengiri(KBK) Odisha2003-04Ongoing13.829471.394145.332119.3290
253Titilagarh Stage - II Medium Irrigation ProjectTitlagarh St-II (KBK) Odisha1998-99Ongoing2.244.1949.706111.422.7
254Naraj Barrage Major Irrigation ProjectNaraj Barrage Odisha2001-02Completed2005-06039.9135.80535.720
255Remodelling of Channels of UBDC System Remodelling of UBDC Punjab2000-01Completed2006-07118177.79299.33164.35100.99
256Extn. of phase II of Kandi Canal (Hosh. to Bala.) Kandi Canal Extension (Ph.II) Punjab2002-03Ongoing23.326300.4392.43175.7917.728
257Ranjit Sagar Dam Major Irrigation Project_Punjab Ranjit Sagar Dam Punjab1996-97Completed2000-010717.48249.79694.830
258Irrigation To H.P. Area Below Talwara Medium Irrigation Project_Punjab Irr. to H.P. below Talwara Punjab2000-01Completed2005-06088.4938.09760.010
259Shahpur Kandi Dam Project Major Irrigation ProjectShahpur Kandi DamPunjab2001-02Ongoing0529.5855.886220.5280
260Gang Canal ModernisationMod. of Gang CanalRajasthan2000-01Ongoing69.694621.42217.738411.868.328
261Bisalpur Major Irrigation ProjectBisalpurRajasthan1998-99Completed2006-071.8224.5141.5661.851.8
262Chauli Medium Irrigation ProjectChauliRajasthan1998-99Completed2006-078.96390.2248.281109.088.96
263Gambhiri Medium Irrigation ProjectGambhiri (Modernisation)Rajasthan1998-99Completed2000-010.9251.951.3151.950.925
264IGNP Stage - II (Rajasthan Canal Stage - II) Major Irrigation ProjectIGNP Stage-IIRajasthan1997-98Ongoing1,0716,001.93582.724,122.7407
265Jaisamand (Alwar) Irrigation ProjectJaismand (Modernisation)Rajasthan1996-97Completed2000-012.3987.683.1257.682.398
266Mahi Bajaj Sagar Unit - II Major Irrigation ProjectMahi Bajaj SagarRajasthan1999-2000Completed2006-0718.406214.417113.652890.9618.406
267Narmada Canal Major Irrigation Project_RajasthanNarmada CanalRajasthan1998-99Ongoing245.8811,855.111,029.0521,445.33216.093
268Panchana Medium Irrigation ProjectPanchanaRajasthan1997-98Completed2004-056.10680.7543.37759.486.106
269Gumti Medium Irrigation ProjectGumtiTripura1996-97Ongoing7.6258.8140.64736.424.765
270Khowai Medium Irrigation ProjectKhowaiTripura1996-97Ongoing9.3253.3433.53949.9628.642
271Manu Medium Irrigation ProjectManuTripura1996-97Ongoing7.658.3752.10240.023.185
272Modernisation Of Lahchura Head WorksMod. of Lachhura DamUttar Pradesh2005-06Ongoing14.575272.7166.903242.52931.91
273Modernization Of Agra CanalMod. of Agra CanalUttar Pradesh2002-03Completed2008-0935150.17744.619135.75337.8
274Arjun Sahayak ERM Scheme XI PlanArjun SahayakUttar Pradesh2009-10Ongoing44.381741.38307.896204.9280
275Restoration of Sarda Sahayak Canal SystemRestoring Cap. of Sarda SahayakUttar Pradesh2009-10Ongoing790319.2339.37585.5105.56
276Restoration/Improving intensity of Hardoi BranchImproving Irr. Intensity of Hardoi Branch SystemUttar Pradesh2006-07Ongoing95.961100.55424.79156.15683.188
277Gunta Nalla Medium Irrigation ProjectGunta Nala Dam Uttar Pradesh1996-97Completed1999-20003.881.311.33.88
278Sharda Sahayak Major Irrigation ProjectSarda SahayakUttar Pradesh1996-97Completed2000-01388.46268.3131268.3366.68
279Kachnoda Dam Major Irrigation ProjectKachnoda DamUttar Pradesh2009-10Ongoing10.8562.5464.675164.23.255
280Rajghat Canal Major Irrigation ProjectRajghat CanalUttar Pradesh2000-01Completed2008-0943.353218.6470.168196.9241.005
281Madhya Ganga Canal Stage - I Major Irrigation ProjectUpper Ganga including Madhya Ganga CanalUttar Pradesh1996-97Completed2003-0454.175393.07233.69393.0752.377
282Eastern Ganga Canal Major Irrigation ProjectEastern Ganga CanalUttar Pradesh1999-2000Completed2010-1172.286583.85194.872594.4569.125
283Saryu Nahar Pariyojana Major Irrigation ProjectSaryu NaharUttar Pradesh1996-97Completed2009-105056,323.29828.6192,118.983563.8
284Upper Ganga Canal Major Irrigation ProjectUpper Ganga including Madhya Ganga CanalUttar Pradesh1996-97Completed2003-0454.175393.07233.69393.0752.377
285Banganga Canal Major Irrigation ProjectBansagar CanalUttar Pradesh1997-98Ongoing150.132452.275687.958492.3150
286Gyanpur Pump Canal Major Irrigation ProjectGyanpur Pump Canal Uttar Pradesh1999-2000Completed2001-021.547.3530.947.351.5
287Madhya Ganga Canal Phase - II Major Irrigation ProjectMadhya Ganga Canal Ph-IIUttar Pradesh2007-08Ongoing146.532946.315176.585463.8433.96
288Jarauli Pump Canal Major Irrigation ProjectJarauli Pump CanalUttar Pradesh2003-04Completed2006-0739.74818.837.07116.48217.625
289Providing Kharif Channel in Hindon Krishi Doab Providing Kharif Channel in H.K. DoabUttar Pradesh1996-97Completed2004-0511.04114.9573.27124.16411.038
290Rajghat Dam Irrigation Project_Uttar Pradesh Rajghat Dam Uttar Pradesh1996-97Completed1996-97042.20360
291Lakhwar Multipurpose Project_UttrakhandLakhwar VyasiUttrakhand1997-98Deffered0578.42012.160
292Tehri Dam (Irrigation Share) Irrigation ProjectTehriUttrakhand1999-2000Completed2006-072701,011.44977.510
293Modernisation of DVCMod. of Barrage and Irri. System of DVCDamodar Valley CorporationWest Bengal1997-98Completed2007-08896.612140.9381.5784.896
294Kangsabati Major Irrigation ProjectKangsabatiWest Bengal1997-98Completed2001-0282.06113.23926.71113.23917.8
295Teesta Barrage, Phase -I, St.I, Sub Stage I Irrigation ProjectTeesta BarrageWest Bengal1996-97Ongoing342.151,001.4331.121369.6588.66
296Subernarekha Barrage Major Irrigation ProjectSubarnarekha BarrageWest Bengal2001-02Ongoing114.1982,862.8913.2881,456.810
297Patloi Medium Irrigation ProjectPatloiWest Bengal2000-01Ongoing2.15812.4315.1175.3770.27
298Hanumata Medium Irrigation ProjectHanumataWest Bengal2000-01Completed2009-101.2543.1381.7833.0381.189
299Tatko Medium Irrigation ProjectTatkoWest Bengal2000-01Ongoing1.19812.2495.9783.5530.674

(Source: India-WRIS WebGIS)
Personal tools
Namespaces
Variants
Actions
Navigation
Topics
Toolbox

Either scripts and active content are not permitted to run or Adobe Flash Player version 10.0.0 or greater is not installed.

Get Adobe Flash Player